A refurbishment and demolition survey (often shortened to R&D survey) is the HSG264 survey needed before any refurbishment, alteration or demolition work. It is fully intrusive within the area of work: the surveyor opens up walls, ceilings, floors and boxing to find asbestos-containing materials that the work would disturb. The area usually needs to be vacated. A management survey is not a substitute. We scope the survey around your project, arrange it with a competent surveyor and help you plan any removal before work starts.
When do you need a refurbishment and demolition survey?
HSE guidance is that this type of survey is needed before any work that will disturb the fabric of a building, other than very minor jobs covered by existing information. Typical triggers include:
- full or partial strip-outs and refurbishments of homes, offices, shops and industrial units;
- new kitchens, bathrooms or heating systems where walls, floors or boxing will be opened;
- rewiring, replacing windows or installing new services through walls and ceilings;
- loft conversions, extensions that break into the existing structure, and knocking rooms together;
- demolition of all or part of a building, including garages and outbuildings.
The survey only needs to cover the area where work will take place, so a small project means a small survey. For demolition, it covers the whole structure. If you are not sure whether your project calls for one, our asbestos surveys overview compares the options, including when targeted sampling is enough.
How is it different from a management survey?
| Management survey | Refurbishment and demolition survey | |
|---|---|---|
| Purpose | Manage asbestos in a building in normal use | Find asbestos before the fabric is disturbed |
| Intrusion | Minimal | Fully intrusive in the area of work, and can be destructive |
| Occupancy | Building stays in use | Area usually vacated |
| Scope | Accessible areas of the whole premises | The specific area being refurbished, or the whole building for demolition |
A management survey is designed to leave the building intact, so it will miss materials hidden behind plasterboard, under floor coverings, inside ducts or within the structure. Those are exactly the materials a refurbishment disturbs, which is why the more intrusive survey exists.
What does the surveyor look for?
Within the area of work, the surveyor inspects and samples anything that may contain asbestos, including hidden layers. In a domestic refurbishment that might mean textured coatings, floor tiles and black adhesive under carpet or vinyl, insulating board panels in ceilings, airing cupboards and behind fires or storage heaters, cement flue pipes and water tanks in lofts, rope seals and gaskets in old boilers, and lagging on older heating pipes. In commercial and industrial buildings the list can extend to sprayed coatings, insulation in plant rooms, board linings to steelwork, roofing and cladding sheets, and fire-break panels.
Samples are analysed by a UKAS-accredited laboratory (ISO/IEC 17025). Because the survey can be destructive, it is usually done once the area is empty and before contractors arrive, and some making good may be needed afterwards if the building is being kept.
Do not let trades start opening up walls, floors or ceilings in a pre-2000 building until you know what is there. If something suspected of containing asbestos has already been broken, stop work, keep people out of the area, close it off and call for advice.
How we arrange a refurbishment and demolition survey
- Understand the project. We ask for the scope of works, drawings or a description of what is being altered, the age of the building and its past refurbishments, and when you need to start.
- Define the survey area. We agree exactly which rooms, floors, roof areas and structures are included so the survey matches the works.
- Written quote. The quote sets out the scope, the intrusive inspection involved, any making good, and access you need to arrange, such as vacating rooms or isolating services.
- Intrusive survey. The survey is carried out by a competent surveyor; we recommend one accredited by UKAS to ISO/IEC 17020.
- Analysis and report. Samples go to a UKAS-accredited laboratory and the report records every material found within the area, with locations, extent and results.
- Plan the removal. We explain which materials must come out before your works, which category each falls into, and how that affects your programme.
Building removal into your programme
The biggest practical benefit of an early survey is time. Materials found in the survey are usually removed before the main works start, so the category of work matters for your timetable:
- Licensed workMost work on insulating board, lagging, sprayed coatings and loose-fill. It must be notified on form ASB5 at least 14 days before it starts and is only ever carried out by an HSE-licensed contractor. See licensed asbestos removal.
- Notifiable non-licensed workSuch as large-scale removal of textured coatings or breaking up cement sheets. It must be notified before work starts. See non-licensed and NNLW work.
- Non-licensed workSuch as carefully removing intact cement sheets. No notification, but still controlled, trained work with proper disposal.
- ClearanceAfter licensed removal inside an enclosure, an independent UKAS-accredited analyst carries out four-stage clearance and issues a certificate of reoccupation. Our air testing and clearance page explains the stages.
Refurbishment surveys across Liverpool and Merseyside
Projects vary hugely across the region. In Liverpool city centre, older commercial buildings are regularly refitted or converted into flats, often with decades of earlier alterations hidden behind modern finishes. In Garston, terraces sit alongside industrial and dock premises, so we see both house refurbishments and strip-outs of older units. Runcorn has 1960s and 1970s new town housing next to older terraces, and both are now reaching the age of major renovation. In Birkenhead, Victorian terraces and conversions are often reworked into modern flats. In each case, knowing what is in the walls before work starts keeps the project moving, and our asbestos removal specialists in Merseyside can take on any removal the survey identifies.
What affects the cost of a refurbishment and demolition survey?
The size of the area being surveyed, the number of floors and rooms, the construction type and how much needs opening up, the number of samples, access to roofs, voids and plant, whether services must be isolated, and any making good afterwards all influence the quote. For demolition, the whole structure is in scope. Our asbestos removal cost guide explains how survey and removal costs fit together so you can budget the project properly. For larger commercial schemes, see also our commercial asbestos removal page.
Planning works on an older building?
Call 07777 659786 or leave your details. Tell us what the project involves, which parts of the building are affected and when you hope to start, and we will call you back to scope the survey.
Frequently asked questions
Do I need a refurbishment survey for a domestic renovation?
If your home was built or refurbished before 2000 and the work will disturb walls, ceilings, floors or the loft, knowing what is there first is strongly advisable, and builders working in your home must take steps to prevent exposure. For a small, specific job, targeted sampling may be enough. For a larger renovation, a survey of the work area is the safer route.
Can I stay in the property during a refurbishment and demolition survey?
Usually the area being surveyed should be vacated, because the inspection is intrusive and can disturb materials. In a house, that may mean emptying certain rooms or, for whole-house surveys, staying elsewhere on the day. We explain what is needed when we scope the survey.
Will the survey damage my walls and floors?
It can. To find hidden materials, the surveyor may need to lift floor coverings, open boxing, cut small inspection holes in plasterboard or remove panels. Because the area is being refurbished or demolished anyway, this is normally acceptable. Any making good is agreed in the quote.
How long before my works should I arrange the survey?
As early as possible. If the survey finds licensable material, it must be notified on form ASB5 at least 14 days before removal can begin, on top of the time for the survey and lab results. Building that into your programme early avoids contractors stopping halfway.
Does a refurbishment survey cover the whole building?
Only the area where work will take place, unless the building is being demolished. If your project expands to other rooms or floors, those areas need surveying too before work starts there. We agree the boundaries with you at the start so nothing is missed.
Can my builder use an old management survey instead?
Not for refurbishment or demolition. A management survey is minimally intrusive and does not look inside the structure. It is useful background, but HSE expects a refurbishment and demolition survey of the area of work before it is disturbed. Talk to our asbestos removal Liverpool service if you are unsure what you have.